Clearing land for a house follows a set order: survey and permits, an 811 utility locate, clearing trees and brush, grubbing out stumps and roots, stripping topsoil, rough grading, and then building the pad to the plans. Doing these out of order (for example, building a pad before roots are out) is the most expensive mistake on a new homesite.
Step 1: Survey the Lot and Mark the House
Start with a boundary survey so you know exactly where the property lines and easements are. Then have the house footprint, driveway, septic area (if any) and utility routes staked. Clearing too much costs money and can violate setback or tree rules; clearing too little means bringing equipment back. Mark the trees you want kept with flagging tape the crew cannot miss.
Step 2: Check Permits and Tree Rules
Inside city limits, many DFW cities require a tree removal permit or mitigation for protected trees over a certain trunk size, and some require a grading or site development permit. Unincorporated county land usually has fewer rules, but floodplain areas, septic permits and driveway access onto county or state roads still need approval. Check before the first tree comes down, because mitigation after the fact is costly.
Step 3: Request an 811 Utility Locate
Texas law requires an 811 locate request before any excavation, including grubbing stumps. Submit it at least two business days ahead. Utility owners mark their lines with paint or flags; private lines (a well line, a line to a barn) are not marked by 811 and need a private locator or the owner's knowledge.
Step 4: Clear Trees and Brush
Dozers, excavators and mulchers remove trees and brush from the build area, driveway and work space around the house. In North Texas that usually means cedar (Ashe juniper), mesquite, post oak and brush. Choose the debris plan up front:
| Debris method | Best for | Watch out for |
|---|---|---|
| Haul off | Tight lots, city limits, anywhere burning is not allowed | Highest cost per acre |
| Forestry mulch on site | Areas that stay wooded or open (not under the house) | Mulch must be stripped from building and driveway areas |
| Burn piles | Rural acreage where rules allow | TCEQ rules, county burn bans, smoke near neighbors |
For typical market costs by density and method, see our land clearing cost per acre guide.
Step 5: Grub Stumps and Roots
Grubbing pulls stumps and the main root mass out of the ground anywhere a structure, driveway or pad will sit. Grinding a stump to ground level is fine for a lawn; it is not fine under a slab, because the roots left behind rot and leave voids that settle. Mesquite will also resprout from roots left in the ground. Backfill the holes with compacted soil, not loose dirt. Our guide on checking for tree roots before filling or grading covers what to look for.
Step 6: Strip the Topsoil
The top few inches of soil hold organic matter, roots and leaf litter that compress and decay. Under a house pad or driveway, that layer comes off and is stockpiled. It goes back on the finished yard later, which saves buying topsoil for the lawn.
Step 7: Rough Grade the Site
Rough grading cuts high spots and fills low spots to bring the lot close to the plan elevations, sets the general drainage pattern, and gets the pad area ready. If the site does not balance, this is where fill is imported or excess dirt is hauled off. See rough grading vs finish grading for how the two passes differ.
Step 8: Build the House Pad
The pad is built to the elevation and spec on the plans and the geotechnical report: often removal or moisture-conditioning of native clay, then select fill placed in compacted lifts with density testing. Pad volume is length × width × height ÷ 27, plus a compaction allowance. Our house pad cost guide has fill volumes for common pad sizes.
Step 9: Driveway Base, Erosion Control and Finish Grade
A construction entrance or driveway base keeps trucks out of the mud. Silt fence or other erosion controls go where runoff leaves the site. Finish grading (setting the final slope away from the foundation, at least 6 inches of fall in the first 10 feet under the IRC) comes after the house is up and the heavy traffic is done.
How Long Does It Take to Clear a Lot?
A lightly wooded one-acre lot can often be cleared and rough graded in a few days of equipment time. Heavy timber, large stumps, wet weather, burn bans or permit waits stretch it to weeks. Pad construction then depends on fill volume, testing schedules and weather, since wet clay cannot be compacted properly.
Common Mistakes to Avoid
- Grinding stumps under the house footprint instead of grubbing them out.
- Building the pad on topsoil or mulch.
- Clearing before checking tree ordinances.
- Driving heavy equipment over the root zones of trees you want to keep.
- Skipping the 811 request on rural land because there are no visible utilities.
Clear, Grade and Pad Your DFW Lot
We handle land clearing, site preparation and building pads across DFW, and we deliver the select fill and fill dirt the pad needs. Every job is quoted per job: send the address, survey, plans and soils report through the bid form on our land clearing page, which accepts plan uploads. Need to size fill first? Use the fill dirt calculator or text (469) 253-2403.