Building Pad Fill Calculator

A pad's fill volume includes its sloped sides, not just length × width × height. A 60 × 50 ft pad, 2 ft high with 3:1 side slopes, is about 275 compacted cubic yards; with a 20% compaction allowance, order about 330 yards of select fill.

Percent. Loose fill shrinks 15–25% when compacted

What to order

  • Structural / select fill330 yd³

    Pad fill, compacted in 6–8 in lifts. Includes 20% allowance · ≈429 tons · 33 tandem loads

    330 yd × $20/yd = $6,600

Compacted volume
274.7 yd³
Added by side slopes
52.4 yd³
Footprint at the base
72 × 62 ft

Delivered price in your city

Materials delivered, starting at$6,600

Published starting prices; each material is a separate load with a 10-yard minimum. Dispatch confirms with your address. Spreading and compaction are not included.

or text (469) 253-2403

How it's calculated

  1. Top area = pad length × width. With side slope S:1, the base grows by 2 × S × height in each direction.
  2. Volume uses the prismoidal formula: height ÷ 6 × (top area + base area + 4 × mid-height area). It is exact for a sloped rectangular pad.
  3. Divide cubic feet by 27, then add 15–25% because loose fill compacts. Your soils report and engineer set the material, lift thickness and density.

Common sizes

ProjectStructural / select fill (yd³)
40 × 30 ft shop pad, 1 ft, 3:164
60 × 50 ft house pad, 2 ft, 3:1330
60 × 50 ft, 2 ft, formed edges267
70 × 50 ft house pad, 3 ft, 3:1626

Yards to order, allowances included, rounded up.

Weight and delivered price per yard

MaterialTons per yd³Yd³ per tonDFW fromDenver from
Structural / select fill1.2–1.40.77$20/yd$25/yd
Fill dirt1.1–1.30.83$10/yd$15/yd

Weights are typical; wet material is heavier. Prices are published starting prices, delivered, 10-yard minimum. Other metros: see your city's service page.

Common questions

How much fill do I need for a house pad?

Typical home pads take 150 to 600 cubic yards. A 60 × 50 ft pad 2 ft high with 3:1 slopes needs about 330 yards of select fill, compaction allowance included.

Why do side slopes matter so much?

The slopes add a wedge of fill all the way around. On a 2 ft pad with 3:1 slopes that is about 52 extra yards, almost a quarter more than the flat-box math.

What fill goes in a building pad?

Select or structural fill as specified in the soils report, placed in 6–8 in lifts and tested for density, typically to 95% Standard Proctor. Native clay is usually not allowed under slabs in North Texas.

How much should I add for compaction?

Plan 15–25%. Loose select fill shrinks when it is rolled to spec, and running short mid-pad costs a day.

Do you build pads too?

In DFW, yes: we build pads to your plans and soils report as part of our site work, quoted per job. Elsewhere we deliver the fill.

Related guides

More calculators

Not sure what to order?

Text your measurements and a photo of the area. We'll tell you the material, the yards, and the delivered price. DFW: text (469) 253-2403 · Denver: text (720) 577-5016.

Your project starts with
the right dirt.

Text us what you need. Quoted in minutes. Delivered in hours.

Text for instant quote

Mon–Sat 7am–5pm · Responses in minutes